Biala Wind Farm Turbine Delivery Information
Turbine component delivery commenced on Thursday 19th March and finished on Friday 31st of July 2020.
Approximately 350 components were delivered from Port Kembla using specialist trucks operating in accordance with guidance from Roads and Maritime Services, the Upper Lachlan Shire Council and NSW Police who escorted the larger deliveries.
To view our collection of construction and turbine delivery images, please click here.
Delivery News
31st July 2020
Wind turbine oversize deliveries to site are now complete. Approximately 350 components have been delivered to site since March. To date, 15 of the 31 turbines at Biala Wind Farm have been erected. Thank you for your patience. For more information, please call 1800 370 045.
25th March 2020
The first turbine blade arrived onsite today. Thanks for your patience. Deliveries will continue through until Saturday. There will be no deliveries on Sunday. Deliveries will restart on Monday (30/03/20). For more information, call 1800 370 045 or click here.
23rd March 2020
Turbine component deliveries are expected to commence on Wednesday this week. Up to 20 deliveries per week are expected to occur from Mon-Sat. Deliveries will travel from Port Kembla to Goulburn via the Hume Hwy, onwards to Crookwell via Crookwell-Goulburn Road, bypassing the Crookwell town centre via Grange Rd, Cullen St, Kialla Rd and Range Rd through to Grabben Gullen Rd and arriving at site. A route map can be downloaded from here.
Deliveries of oversize components are expected to arrive in Goulburn at 5:30am. Between 6am and 9am they will travel from Goulburn to the wind farm site. Please consider using alternative routes where possible during these times to avoid delays. We are grateful to the community for their patience. For more information call 1800 370 045.
18th March 2020
BJCE Australia would like to advise the local community that turbine component deliveries scheduled to arrive tomorrow (19/03/2020) have been delayed until next week. We will continue to keep you updated. For more information about the turbine deliveries, click here or call 1800 370 045.
13th March 2020
Turbine component delivery is expected to commence Thursday 19th March. Approx 350. Components will be delivered on specialist trucks from Port Kembla to the wind farm for 20 weeks. Up to 20 deliveries per week are expected to occur from Mon-Sat. We will continue to provide regular updates. A fact sheet can be downloaded from our website www.bialawindfarm.com. For more information call 1800 370 045.
Deliveries will travel from Port Kembla to Goulburn via the Hume Hwy, onwards to Crookwell via Crookwell-Goulburn Road, bypassing the Crookwell town centre via Grange Rd, Cullen St, Kialla Rd and Range Rd through to Grabben Gullen Rd and arriving at site. A map can be downloaded from our website. Delays can be expected and we are grateful to the community for their patience.
Deliveries of oversize components are expected to arrive in Goulburn at 5:30am. Between 6am and 9am they will travel from Goulburn to the wind farm site. Please consider using alternative routes where possible during these times to avoid delays.