About the Project

Summary

The proposed Biala Wind Farm (the Project) is located approximately 8km east of Biala and 14.5km south west of Crookwell in the Southern tablelands of NSW. It is owned by Beijing Jingneng Clean Energy (Australia) Holding Pty Ltd (BJCE Australia) who also owns the nearby Gullen Range Wind Farm and Gullen Solar Farm.

The wind farm is expected to have an installed capacity of approximately 110MW, producing enough electricity for approximately 46,000 typical homes on an average day of wind.

When constructed the wind farm is proposed to consist of 31 turbines and associated infrastructure, including the following:

  • Wind turbines – BJCE Australia will install 31 Goldwind 3.5MW wind turbines, with a height from the base of the tower to the highest tip of the rotor blades of 180m (ground to blade tip). The turbine towers will be connected to concrete foundations buried in the ground. There will be a small set of electrical switchgear located next to each wind turbine.
  • Access tracks – the locations of the turbines will be linked by gravel tracks. Each turbine location will also include a gravel area to setup the cranes used to lift the turbine components.
  • Electrical cables – turbines will be linked by an underground 33kV electrical cabling and fibre optic communications cabling.
  • Meteorological monitoring masts – up to four masts will be constructed to enable monitoring of wind speed and direction.
  • Ancillary facilities – a maintenance and storage shed will be constructed together with a site office and car parking facilities.
  • Substation/switchyard – Biala Wind Farm will be connected to the existing Gullen Range Wind and Solar Farm substation/switchyard via an underground Transmission Line. Use of the existing Gullen Range Wind and Solar Farm infrastructure avoids the impact of constructing a new substation. A minor extension to the existing substation will be required to accommodate the additional energy from the Biala Wind Farm.
  • Transmission Line – in order to transmit energy from Biala Wind Farm to the national electricity grid, a 12km underground 33kV transmission line between Biala Wind Farm and our existing Gullen Range Wind and Solar Farm substation/switchyard will be constructed. To minimise environmental impacts and the ability to farm the land, the transmission line will be placed underground. You can find out more about the transmission line here.

You can view the location of the proposed wind farm here.

 

Development

BJCE Australia acquired the Biala Wind Farm from Newtricity Developments Pty Ltd (Newtricity) in October 2017.

Newtricity submitted an application for development approval for the Wind Farm in 2015. Development Approval (Consent) was obtained from the NSW Planning Assessment Commission on 12th April 2017 and can be viewed here. The Development Consent was granted under the provisions of section 89E of the Environmental Planning and Assessment Act (1970).

For details of other documents considered by the Department of Planning and Environment (DPE) when the wind farm was approved, please visit the DPE website by clicking here.

The Development Approval for the wind farm does not include the infrastructure required to connect to the electricity network. A development application was submitted to Upper Lachlan Shire Council in November 2017 for an underground 33kV electricity connection to the existing Gullen Range Wind and Solar Farm substation. An extension to the existing Gullen Range Wind and Solar Farm substation is part of this application. The development application was approved by the Southern Regional Planning Panel (JRPP) on 17th January 2019 subject to conditions. The approval and conditions were subsequently issued by the Upper Lachlan Shire Council. Further information is available on the Planning Panel’s website here, including the documentation submitted by Biala Wind Farm. The Development Approval issued by Upper Lachlan Shire Council can be downloaded here. You can find out more about the transmission line here.

 

Construction

BJCE Australia started building Biala Wind Farm in August 2019. Construction of the wind farm will take approximately 16 to 18 months to complete.

To keep you informed about the construction progress, we are providing regular updates on three main construction areas in the timeline below and in our monthly newsletters, which you can read here. The construction areas are as follows:

  • Area One: Biala Wind Farm Site, which is located on the western side of Grabben Gullen Road, with two entrances to site approximately 6 km and 8.5 km south of Grabben Gullen.

 

  • Area Two: Extension to the Gullen Range Wind Farm substation, which is located in Bannister. The extension to the existing substation will be required to accommodate the additional energy transmitted from the Biala Wind Farm.

 

  • Area Three: Electrical Transmission Line between Biala Wind Farm and Gullen Range Wind Farm. Biala Wind Farm will connect to the electricity grid via underground electricity cables from the Gullen Range Wind Farm substation at Bannister. The transmission line will be approximately 12 km long and will consist of four electrical cables.

 

To view a map of the construction areas, please click here.

 

Indicative Project Timeline

Project Construction Area Project Stage Estimated Completion
Roadworks to Kialla Road Complete
Roadworks to Range Road Complete (pending final seal and road markings)
Area One Site Entrances on Grabben Gullen Road Complete
Area One Onsite civil and electrical work August 2019 to May 2020
Area One Delivery and erection of wind turbines February 2020 to September 2020
Area One Commissioning of wind turbines March 2020 to November 2020
Area Two Substation extension October 2019 to March 2020
Area Three Installation of  underground electrical transmission line October 2019 to February 2020

 

For more detailed construction updates, please check out our monthly newsletters here.

 

Transportation Routes

The Development Approval defines the transportation routes to be used during the construction phase. Oversize loads will be transported to site via Goulburn and Crookwell, while other heavy goods will travel from the Hume Highway via Gunning. You can download a map of the routes here. Please note that the ‘pavement upgrade’ options labelled on the map will be completed. We have developed a detailed traffic management plan, which is available here . It has been agreed with Roads and Maritime Services (RMS) and Upper Lachlan Shire Council.

 

Text Message Service

If you live nearby and are interested in receiving construction or project updates by text message to your phone, please contact us here.

 

Subcontractor and Accommodation Provider Opportunities

If you are a sub-contractor interested in taking part in the project or you are a local with accommodation you would like to offer to wind farm staff, you can register your details here and we’ll pass on your details to our contractors.

 

Images of Construction Progress

 

October 2019